Repetition, Communication, and Coordination: A Modular QSR Case Study

Modular construction has always required extra coordination and decision-making before finalized units are installed on site. Many manufacturers and designers have developed their own processes, with critical iterating to make sure the product arrives in one piece.

Now imagine ensuring successful repetition with a quick service restaurant (QSR) module that is 95 percent built in a factory. Then imagine shipping, delivering, and installing it on a foundation, with the goal of having the restaurant operating as soon as possible. That means installing in weeks, not months.

So, what’s the magic behind this process? Repetition, communication, and coordination.

modular QSR rendering

Renderings of single-story modular QSR buildings from sgblocks and CSHQA.

Dan Gelatt, Director of Business Development and Field Operations at Safe & Green Holdings Corp., and Jesse Goldman, Principal Architect at CSHQA Architects figured out a working formula to bring their QSR design from paper to reality, with all the critical information included to ensure no screw remained loose.

At this year’s (2024) World of Modular, both Goldman and Gelatt will be presenting their case study on the design, delivery, and installation of this QSR as a super-wide module.

Leading up to Modular, Then to Quick Service Restaurants

Before jumping onto this particular project, Goldman headed his own firm with a diverse background in architecture before joining CSHQA and partnering with Safe & Green Holdings for the first time on a modular project. He found that he “really liked the puzzle of it.”

“I’ve worked on a multitude of different projects, anything from arenas to healthcare, offices, restaurants,” he said. “I really liked the idea of trying to figure out the multiple layers of construction that modular provides.”

Gelatt’s experience in the construction business spans over 20 years, both working in conventional and the modular space, before landing his spot at Safe & Green Holdings. From there, he was exposed to container modifications and worked with David Cross, whom he calls “the leader in that space.”

According to David Cross, VP of Business Development at Safe & Green Holdings, QSR projects take up about five percent of the current portfolio “with a commitment to growth.”

The corporation expanded with SG Echo LLC, a Modular Manufacturer, with two locations in Oklahoma. Both of these factories have over 55,000 square feet of production capacities.

The Tough Work of Communication and Coordination

QSR-Renderings-5_1200x600
modular QSR rendering

CSHQA and Safe & Green Holdings seemed almost destined to work together, given each company’s portfolio backgrounds. CSHQA has a lot of experience with restaurant work (QSR work) and has a strong modular background, according to Jesse.

“There is a good marriage of projects right there,” he said. “This just made a lot of sense from our team and from the SG team to move forward with this project and start developing a product that was a little bit different than potentially what some of our competitors are producing, both in the architectural order and the factory side.”

Each company’s background laid out the foundation, but the continued dedication to open communication and coordination is what keeps the partnership humming, according to Dan.

“We value each other’s opinion and incorporate it into the design,” said Gelatt. “The key is the coordination of the drawings, calling out the scopes and responsibilities on the drawings, listening to what it takes to complete the work within a factory, and onsite. Incorporating those into the design makes it more efficient and it eliminates finger pointing.

”On top of constant and open communication between the companies, there is also the matter of making sure that all relevant parties are updated and are able to adapt and respond in kind. This requires a lot of thinking ahead," said Gelatt.

Making the Usual More Unusual

The workload between the design firm and the manufacturer was set. The two communicated constantly, with Gelatt providing on-the-ground updates as the module was being delivered and installed.

“I’ll be out in the field during the install so I can come back and give feedback,” he said. “That way, I can tell the design team and the factory ‘hey this worked really well, let’s keep it.’ ‘Let’s, look at tweaking this? This is what happened when we did this.’”

Taking the standard parameters and design elements of a QSR and shipping it by a double-drop deck trailer as one cohesive prefabricated functional unit took some creative thinking. Which is where Jesse and his team at CSHQA came in. How could they place a unit that was about 16 feet and 10 inches wide and 40 feet in length?

“We need more detail, more understanding and more accuracy in our drawings on some of these,” said Goldman. “We’re looking at plumbing accuracy to the quarter of an inch, whereas that’s well beyond the accuracy or what we would ever draw on a stick-built building.”

Considerations for Installing a QSR Module

Modules can be installed in any number of ways, especially if you’re working with multiple units. The decision to deliver it as a whole unit however, eliminated the need to address matelines. It also left the question of how to install the unit upon arrival. The size of the unit also made setting a bit thornier.

“Traditionally if you were doing more of a traditional modular retail housing unit, you would never go up to that wide. You would bring in multiple units and have a mateline in between the units,” said Goldman. “What was different and what made this effective with the QSR model was not having that mateline and reducing the time it took to set the unit and to not have to see together two units, which would take a week or two that let them start selling products sooner.”

Keeping efficiency in mind, Goldman and CSHQA decided that a top-picked unit was the way to go.

Delivering a Super Wide Module Across the Country

As the QSR was delivered whole to reduce time spent on setting the module on the foundation, that created another series of obstacles. There was the matter of how to ship the parapet. If the parapet was connected from the get-go, the unit would be too tall to ship.

In the end, the top pick served a two-fold purpose.

“Jesse and his team took it a step further where that top pick is that connection,” said Gelatt. “Now we’re sticking the parapet over top of it and now reusing that connection to fasten down the parapet to the modular building. It’s that type of thinking that leads to the success of the project, the efficiency of the project.”

While the dimensions were not completely out of the norm for a module, driving a module that was a little over 1600 feet wide by 40 feet in length was going to be another puzzle to sort out. Ultimately it was decided that the unit would travel on a double drop deck trailer.

The first one shipped from Durant, Oklahoma to Osceola, Arkansas—a distance of at least 500 miles. The third one is making an even longer trip out to the Pacific Northwest, or about 2,000 miles.

Repetition Makes the Dream Work

Dan Gelatt
jesse-goldman_500x500

Presenting Modular QSR at World of Modular

Daniel Gelatt, Director of Business Development & Field Operations, Safe & Green Holdings Corp.
Jesse Goldman, Principal Architect, CSHQA Architects

All stakeholders can benefit from the in-depth process and tight-knit relationship required for modular building projects: owners, developers, architects, manufacturers, city officials, plan examiners, general contractors, anyone in the construction industry. Both Gelatt and Goldman ultimately want attendees to gain new insight—or at least new ideas—on how to make modular happen.

“I want them to take away that this is a viable alternative to what they’ve been looking at,” Goldman said. “That there are other ways of doing this and we’re exploring these other ways to make it even more viable...it’s a continuous operation of becoming better and making these better and making them more economical and ultimately making more money for the people who decide to take this route.”

And Dan agrees.

“They have another tool in their toolbox that is an alternative to conventional construction. It’s going to be structurally sounder, and it’s going to be just as efficient,” he said.

Coming back to the drawing table after the project was completed and keeping an open mind is also what allowed the success of these projects, according to Gelatt.

“You want to repeat the process, have that collaboration, what worked, what didn’t work, what made sense, what didn’t make sense,” said Gelatt. “Especially with QSRs, thinking about the workflow of the interior space, there’s a lot of detail that you have to go through each and every time. And that’s why, again, the partnership and collaboration have to be there.”

About the Author: Dawn Killough is a freelance construction writer with over 25 years of experience working with construction companies, subcontractors and general contractors. Her published work can be found at dkilloughwriter.com.

More from Modular Advantage

A Huge Win for the Modular Construction Industry in Massachusetts

In early February, 2024, the Massachusetts Board of Building Regulations and Standards (BBRS) released its proposed 10th Edition building codes. This draft included several amendments targeting modular construction that would have created an extremely difficult environment for the entire modular industry and could have eliminated the industry entirely in the state.

FEMA Announces Hawaii Housing Plan Using Modular Construction

Utah becomes the second state in the country, following Virginia, to fully adopt ICC/MBI standards 1200 and 1205. MBI will continue to work with leadership in Utah to implement the new program.

Supply and Demand: Solving Canada’s Housing Crisis One Relocatable Housing Unit at a Time

Not only do Moda Modular’s repurposed employee housing solutions cut the emissions related to construction down to nearly zero, but they also keep building materials that are often not biodegradable from slowly decaying in storage facilities.
It’s the classic environmental mantra of reduce, reuse, and recycle, scaled up and applied to building after building.

ICC/MBI Standards 1200 & 1205 Provide Foundation for Utah’s First-Ever State Modular Program

Utah becomes the second state in the country, following Virginia, to fully adopt ICC/MBI standards 1200 and 1205. MBI will continue to work with leadership in Utah to implement the new program.

Modular Architecture: Thinking Outside of the Box with Sara.Ann Logan

At a time when modular buildings were still seen as less than by many in the architecture and construction world, Sara.Ann Logan took the plunge and partnered to launch a design-build firm that designed, built, and constructed modular high-end single-family homes. But even though she could see the value of this kind of construction, it wasn’t universally accepted.

Colorado Developer ‘Attacks’ Attainable Housing Crisis

City, county, and state government bodies are reaching out to Fading West Development, a modular manufacturer and developer in Buena Vista, CO, to learn more about how they are using modular construction to solve the affordable housing crisis in Colorado. Governments are eager to learn how they’ve made modular development successful and profitable while meeting the growing need for affordable housing.

CES Group’s Stuart Cameron Will Convince You the Moon Is Achievable with Modularized MEP

While most people think of construction as a gradually layered process, MEP assemblies—such as the modular ones—tend to provide all-in-one installs, like a car factory. A modular MEP product helps developers, architects, and fellow modular manufacturers reach their goals through early integration and planning. MEP assemblies address all the unseen things like electrical, heating, and plumbing when looking at a finalized building. The very nature of MEP assemblies are crucial to any initial prospectus.

Automation: The Future for Offsite Modular Construction

Offsite modular construction lags far behind other industries in embracing and adopting automation. Some people believe it will decrease jobs. Others feel they’ve done okay without it, so why change? In reality, conventional construction methods simply cannot keep up. Cooper Lane of Brave Control Solutions points to the labor shortage and the housing crisis that’s rampant in Canada, the U.S., and globally.

Seizing the Modular Construction Opportunity

The CSA Public Policy Centre’s new report, Seizing the Modular Construction Opportunity, highlights how innovative modular methods can help to bring various building forms—from single unit housing to complex high-rises—online more quickly. Owing to efficient manufacturing practices and controlled factory environments, modular can achieve completion rates that are 25% to 50% faster than conventional construction approaches.

Structural versus Cyclical: What Matters More?

A new set of considerations have induced leaders of major global manufacturing enterprises to reconsider their site selection decisions. Among these are: 1) a desire for simpler logistics emphasizing shorter transit distances and times; 2) a need to better protect intellectual property; 3) more reliable court systems; 4) incentives offered by the USMCA, America’s trade deal with Canada and Mexico; and 5) a recent set of subsidies offered under packages like the Chips and Science Act and the Inflation Reduction Act.