Parkhurst Elementary School Modular Classroom Additions
The Parkhurst Elementary School in Winchester, MA, has recently undergone an expansion of 13,074 square feet. Due to renovations at the neighboring Lynch School, students were temporarily relocated to Parkhurst. Modular construction was chosen as the preferred method to accommodate the influx of students and prepare for the start of the 2023-2024 school year.
Lynch Elementary School at Parkhurst serves 466 students from kindergarten to grade five. The newly added space includes 15 modules set in the old faculty parking lot. The modular classrooms were strategically placed to ensure compliance with state codes and to maximize available space. Each classroom is spacious and equipped with motion-sensing lights and conduits to install the necessary tech for the teachers. To ensure staff comfort, the design includes two faculty restrooms, multi-stall boys’ and girls’ bathrooms. The original RFP proposed an aluminum ramp to connect to the new parking lot, but Triumph Modular proposed a redesign that included an asphalt walkway with a gentler incline. This new walkway leads to a larger parking lot for staff and buses, with a designated drop-off area for the students. Subcontractors installed black powder-coated steel handrails on the aluminum decking, creating a seamless transition between the asphalt and the ramp while maintaining ADA compliance.
Despite challenges such as the unusually rainy summer season and the removal of a large amount of ledge from the site of the new parking lot, the project was completed on time and within budget. Triumph Modular’s expertise and ingenuity, as well as careful planning and logistical mapping, ensured that the project was a success. The town administrators were highly collaborative and worked with us when issues arose during the project.
The success of this project was made possible due to open communication with the municipalities and neighbors. Triumph Modular is proud to have been a part of the Winchester community and provided the children of Lynch Elementary School at Parkhurst with a safe and quality learning space for the next two years.
The Challenge
- The classroom modules are placed in the existing school parking lot.
- Constrained site space for the modular classrooms.
- Unusually rainy season, delaying scheduled work and potentially impacting cost.
- Thickly settled neighborhood.
- Narrow and sloped delivery route for the modular classrooms.
The Solution
- Creating a parking lot by paving over a baseball field.
- Each unit had to be designed individually creating variable classroom sizes.
- Negotiating with sub-contractors.
- Our site supervisor constantly and consistently communicated with neighbors. Making them aware of upcoming work and any impact.
- Several logistical plans routed to account for roads and trees.
The Results
- A long-term permanent solution with additional parking spaces and a safer bus drop-off area for students to get into school.
- The units were able to fit perfectly in the allotted space and maintain code compliance.
- Our schedule stayed on track and our bid met budget.
- Collaboration and communication with the town municipalities and administration.
- Units were delivered without issue by smaller toters.
More from Modular Advantage
Resia: Breaking All the Rules
Resia Manufacturing, a division of U.S.-based Resia, is now offering prefabricated bathroom and kitchen components to industry partners. Its hybrid fabrication facility produces more precise bathroom and kitchen components (modules) faster and at lower cost than traditional construction. Here’s how Resia Manufacturing does it.
How LINQ Modular Innovates to Bring Modular To The Market in the UAE and Beyond
LINQ Modular, with an office and three manufacturing facilities in Dubai, is a modular firm based in United Arab Emirates. The company is on a mission: to break open the housing and construction markets in the Gulf Cooperation Council (GCC) area with modular.
ModMax: Redefining Modular Construction with Confidence and Precision
ModMax was born out of frustration—frustration with five persistent pain points in modular construction: Permitting bottlenecks. Production delays. Rigid designs. Disconnect between “the office” and the field. Lack of transparency and communication.
LifeArk: Disaster-Resilient Housing from Recycled Plastic and 100-year-old Technology
Wee compares LifeArk’s housing units to Yeti coolers, as they are built similarly. Each component takes 15 to 20 minutes to manufacture, has an R-value of 40, and includes molded slots and chases for wiring, plumbing, fire sprinklers, and other utilities.
Building the Future of Modular Edge Infrastructure
The edge data center market is expanding rapidly, driven by the surge in AI workloads, IoT adoption, and the need for localized compute power. In these environments, sustainability, scalability, and reliability are non-negotiable. Cooling is among the most complex challenges for operators—and one of the most decisive factors in long-term success.
Accelerating Light-Gauge Steel Construction: A Semi-Automated Digital Workflow for Off-Site Projects
For construction professionals, the message is clear. By adopting semi-automation and digitalization, companies can deliver projects faster, more accurately, and more profitably, while also building stronger collaboration across teams. The approach is not about replacing people with machines, but about empowering people with better tools and processes.
Why Modular Data Centers Are Gaining Momentum
Artificial intelligence, high-performance computing, and edge applications push the limits of traditional “stick-built” data centers. They take years build, often struggle with high density workloads, and aren’t optimized for deployments near end users. Modular data center platforms are purpose-built to address these challenges, offering flexibility and scalability to adapt to evolving technologies, while opening new opportunities for the modular construction industry.
Supply Chain Innovation in Action: 5 Habits Every Modular Leader Should Practice
By applying these principles to supply chain practices — collaborative planning, strategic procurement, scenario modeling, digital tools, and transparent forecasting — construction leaders can build value chains that are not just efficient and agile, but truly innovative.
Exploring the Role of Modular Integrated Construction (MiC) in Advancing Circular City Principles – A Survey of Stakeholder Perspectives
The survey findings highlight the significant potential of Modular integrated Construction (MiC) in advancing the development of circular cities. By reducing costs, accelerating construction timelines, and minimizing waste generation, MiC offers a promising approach to sustainable urban development.
The Use of MS POLYMER™-Based Sealants and Adhesives in Modular Building
These products combine flexibility and elastic recovery with excellent adhesion to different substrates and have already shown their usefulness in traditional construction. Now it’s time for them to be put to use in the modular construction industry.