Accelerating Light-Gauge Steel Construction: A Semi-Automated Digital Workflow for Off-Site Projects
Amir Mehdipoor, Ph.D. is Team Leader, Industrialized and Digitized Construction, at National Research Council Canada.
Ivanka Iordanova, Ph.D. is Ivanka Iordanova, Ph.D. is a professor in the Department of Construction Engineering, École de technologie supérieure.
Introduction
The construction industry faces a persistent challenge: how to deliver high-quality buildings faster, more accurately, and at a lower cost. Off-site construction (OSC) has long promised these benefits by shifting work into controlled factory settings, where efficiency and safety can be optimized. Within this landscape, light-gauge steel (LGS) has emerged as one of the most promising materials for modular and prefabricated construction. Its strength, adaptability, and consistency make it well suited for repetitive production processes.
Yet despite these advantages, many companies that adopt OSC still struggle to unlock its full potential. This is because too often, off-site factories reproduce traditional manual workflows rather than rethinking processes around digital tools and automation. The result is that productivity gains fall short of expectations.
This industry article is based on our original peer-reviewed study “Enhancing the Manufacturing Process in Light-Gauge Steel Off-Site Construction Using Semiautomation” published in the Journal of Construction Engineering and Management (ASCE, 2025), co-authored with Ivanka Iordanova and Mohamed Al-Hussein. The goal here is to translate our research into a professional industry context, walking readers through the methodology, summarizing the findings, and highlighting key takeaways that practitioners in the LGS sector can apply directly to their projects.
Automated Structural Framing Derived from Architectural Model
Methodology
The study followed the Design Science Research (DSR) method, a structured approach for creating and testing practical solutions in complex environments.
- Problem Identification
The researchers identified three critical inefficiencies in current LGS off-site construction:- Long task durations in manufacturing and assembly.
- Inaccurate Bills of Quantities (BoQs) due to reliance on manual takeoffs.
- Poor coordination between design, production, and assembly teams.
- Solution Design
A semi-automated workflow was developed, combining:- BIM-driven design automation to generate precise models.
- CNC code generation from BIM models to control automated framing machines.
- QR-coded shop drawings allowing assembly teams to instantly access 3D BIM models for guidance.
- A Common Data Environment (CDE) for sharing design files, CNC codes, and updated documents.
CNC-Ready Light Gauge Steel (LGS) Panel Design
Unlike a fully automated approach, this workflow kept human workers engaged for tasks like feeding steel rolls, stacking studs, and assembling panels, balancing automation with flexibility.
- Validation and Assessment
The workflow was tested on a 2,500 m² modular project with 47 modules. Its effectiveness was measured by comparing:- Task durations before and after implementation.
- Accuracy of BoQs from manual versus automated methods.
- Economic feasibility, through a cost–benefit analysis calculating payback time for the required investment.
Findings
The results show that even partial automation, when well-integrated with digital tools, can transform the efficiency of LGS off-site projects.
- Major Reductions in Task Duration
- Average overall reduction: 38.11%.
- Window installation: 58% faster.
- Door installation: 67% faster.
- Roof construction: 50% faster.
- Floor frames and ceilings: up to 30% faster.
Automated CNC-driven fabrication ensured precise cuts and dimensions, which in turn made assembly smoother and quicker.
- Significant Improvements in Quantity Accuracy
- Average improvement: 10.77%.
- For certain components, accuracy improved by as much as 45%.
Manual takeoffs were shown to be highly error-prone, while BIM-based automated takeoffs provided reliable and consistent results.
- Strong Economic Case
-
- Payback period: 10 months and 26 days.
- Savings:
- Labor savings from faster tasks (38% reduction in hours).
- Material savings from more accurate BoQs (11% reduction in cost per area).
This proves that even a large upfront investment in automation, software, and training can pay for itself in less than a year.
- Improved Coordination
The use of a Common Data Environment was a standout factor in project success. Teams could work from one shared source of truth. QR codes embedded in shop drawings allowed workers to scan and view 3D models instantly, reducing miscommunication and ensuring alignment across design, manufacturing, and assembly phases.
Precision Manufacturing of Modular Building Units
Key Takeaways for Industry Professionals
The findings from this study don’t just live in research journals, they have direct, actionable lessons for professionals working in light-gauge steel and off-site construction.
BIM as a Production Backbone
Many firms use BIM primarily for visualization and coordination. This project demonstrates its deeper value as the backbone of production. When BIM models generate CNC codes for machines and shop drawings for crews, the entire workflow becomes more connected and reliable. This reduces rework, shortens timelines, and creates a direct link between design intent and production reality.
Semi-Automation Balances Cost and Flexibility
Fully automated factories may be out of reach for most companies, especially smaller and mid-sized firms. A semi-automated approach, where machines handle repetitive precision tasks while humans oversee flexible, adaptive tasks, offers a practical balance of cost, control, and scalability. This hybrid model delivers measurable efficiency gains without the need for a fully robotic factory.
Accuracy Drives Better Outcomes Than Speed Alone
Time savings are always attractive, but improved accuracy in quantity takeoffs may deliver even greater long-term benefits. Accurate BoQs mean fewer procurement errors, less material waste, and more reliable budgets. This reduces risks of cost overruns and schedule delays. For contractors and developers, accuracy is just as valuable as speed.
Standardization Unlocks Efficiency
Light-gauge steel components are inherently modular, which makes them ideal for prefabrication. But to fully benefit, companies must embrace standardized designs and repeatable processes. The more uniform and modular the components, the easier it becomes to apply digital automation. Firms that invest in standardization can expect faster returns on digital workflows.
Collaboration Requires Digital Infrastructure
One of the most underrated findings is the value of the Common Data Environment. By centralizing models, CNC codes, and documents, it created a single source of truth across disciplines. Features like embedded QR codes bridged the gap between office and shop floor, making digital collaboration tangible for field workers. Without this shared platform, even the best digital tools risk creating silos.
Training and Culture Are Essential for Success
Introducing semi-automation is not just about machines and software, it’s about people. In the case study, extensive training sessions and workshops ensured workers were comfortable using new tools. For success in the real world, companies need to invest in their workforce, build confidence in digital tools, and foster a culture that embraces change rather than resisting it.
The Business Case is Strong, Use It to Win Support
Many firms hesitate to invest in automation because of the high upfront cost. This research provides hard evidence that the investment can pay back in under a year. For decision-makers and stakeholders, this makes a compelling business case: digitalization and semi-automation aren’t just operational improvements, they’re strategic investments in competitiveness.
Start Small, Scale Smart
One practical lesson from the case study is the value of piloting. By testing the workflow on a specific modular project, the team could measure results, build confidence, and refine processes before scaling up. Industry professionals should consider starting with a pilot project that’s manageable in size but representative enough to provide useful insights.
Semi-Automated Production of LGS Modules in Factory Setting
Conclusion
Light-gauge steel off-site construction has always held promise, but too often that promise has gone unrealized because traditional workflows persist in new environments. This research demonstrates a way forward: a semi-automated digital workflow that bridges the gap between design and production, balancing automation with human expertise.
The results are undeniable:
- 38% faster production and assembly.
- 11% more accurate BoQs.
- Investment payback in less than 11 months.
For construction professionals, the message is clear. By adopting semi-automation and digitalization, companies can deliver projects faster, more accurately, and more profitably, while also building stronger collaboration across teams. The approach is not about replacing people with machines, but about empowering people with better tools and processes.
In a competitive industry where time, accuracy, and cost are everything, workflows like this could define the future of light-gauge steel construction.
More from Modular Advantage
Resia: Breaking All the Rules
Resia Manufacturing, a division of U.S.-based Resia, is now offering prefabricated bathroom and kitchen components to industry partners. Its hybrid fabrication facility produces more precise bathroom and kitchen components (modules) faster and at lower cost than traditional construction. Here’s how Resia Manufacturing does it.
How LINQ Modular Innovates to Bring Modular To The Market in the UAE and Beyond
LINQ Modular, with an office and three manufacturing facilities in Dubai, is a modular firm based in United Arab Emirates. The company is on a mission: to break open the housing and construction markets in the Gulf Cooperation Council (GCC) area with modular.
ModMax: Redefining Modular Construction with Confidence and Precision
ModMax was born out of frustration—frustration with five persistent pain points in modular construction: Permitting bottlenecks. Production delays. Rigid designs. Disconnect between “the office” and the field. Lack of transparency and communication.
LifeArk: Disaster-Resilient Housing from Recycled Plastic and 100-year-old Technology
Wee compares LifeArk’s housing units to Yeti coolers, as they are built similarly. Each component takes 15 to 20 minutes to manufacture, has an R-value of 40, and includes molded slots and chases for wiring, plumbing, fire sprinklers, and other utilities.
Building the Future of Modular Edge Infrastructure
The edge data center market is expanding rapidly, driven by the surge in AI workloads, IoT adoption, and the need for localized compute power. In these environments, sustainability, scalability, and reliability are non-negotiable. Cooling is among the most complex challenges for operators—and one of the most decisive factors in long-term success.
Why Modular Data Centers Are Gaining Momentum
Artificial intelligence, high-performance computing, and edge applications push the limits of traditional “stick-built” data centers. They take years build, often struggle with high density workloads, and aren’t optimized for deployments near end users. Modular data center platforms are purpose-built to address these challenges, offering flexibility and scalability to adapt to evolving technologies, while opening new opportunities for the modular construction industry.
Supply Chain Innovation in Action: 5 Habits Every Modular Leader Should Practice
By applying these principles to supply chain practices — collaborative planning, strategic procurement, scenario modeling, digital tools, and transparent forecasting — construction leaders can build value chains that are not just efficient and agile, but truly innovative.
Exploring the Role of Modular Integrated Construction (MiC) in Advancing Circular City Principles – A Survey of Stakeholder Perspectives
The survey findings highlight the significant potential of Modular integrated Construction (MiC) in advancing the development of circular cities. By reducing costs, accelerating construction timelines, and minimizing waste generation, MiC offers a promising approach to sustainable urban development.
The Use of MS POLYMER™-Based Sealants and Adhesives in Modular Building
These products combine flexibility and elastic recovery with excellent adhesion to different substrates and have already shown their usefulness in traditional construction. Now it’s time for them to be put to use in the modular construction industry.
From BIM to Execution: Turning a “Pretty Picture” into a Single Source of Truth for Off-Site Construction
When implemented properly, BIM becomes the company’s digital backbone: connecting teams, standardizing information and transforming data into actionable insights. It is the key to achieving lean, predictable operations where all phases – design, planning, procurement and project execution are empowered by a single source of truth.