Oldivai on 31st – Modular Housing, Rinse and Repeat

What Makes Oldivai Different?

Fast and high-quality construction rarely go together—until now. Oldivai on 31st (aka Project Zero) redefined modular housing by combining speed with exceptional standards. Developed as the inaugural project for Oldivai Capital, this 7,280-squarefoot, three-story complex wasn’t just designed to address Spokane’s growing housing shortage, it was created to serve as a prototype for scalable, repeatable workforce housing solutions.

With a “kit-of-parts” approach, Oldivai on 31st demonstrated how a predesigned layout could deliver consistent programming and rapid deployment. This project didn’t just match the site; it set a standard for matching the design to sites across multiple locations. With five additional projects and a larger multi-unit complex slated for 2025, this proof of concept has already paved the way for future developments.

Quick Facts

  • Project Name: Oldivai on 31st
  • Location: Spokane, Washington
  • Building Type:
    Multifamily Apartments
  • Number of Units: 10
  • Number of Modules: 15
  • Total Area: 7,280 square feet
  • Timeline:
    • Groundbreaking: July
      31, 2023
    • Modular Set: Jan. 29 – Feb. 1, 2024 (4 days)
    • (TCO) Substantial
      Completion: July 2, 2024 (310 days from site start)
  • Total Construction Cost: $2,692,850

Why Modular? Why Now?

Traditional construction simply can’t keep up with the rising demand for housing. Modular construction offers not just a faster solution but a smarter one. Oldivai on 31st tackled inefficiencies head-on, sidestepping weather delays and labor shortages to deliver a completed project in under a year. But this wasn’t just about speed. The real challenge was scalability: could modular construction deliver consistent quality across future developments? Project Zero answered that with a resounding yes, setting a new standard for efficiency, precision, and repeatability in multifamily housing.

Designing for Precision and Efficiency

At Oldivai on 31st, efficiency meant doing things right from the start. Every stage of the process was optimized to maximize quality while minimizing delays. Building modules in a climate-controlled factory protected materials from Spokane’s unpredictable weather. This method reduced waste, ensured tighter tolerances, and allowed interiors, mechanical systems, and finishes to be 80% complete before shipping. Modules arrived on-site nearly move-in ready. Plumbing, electrical systems, and finishes were pre-installed, leaving minimal onsite labor. The modules were craned into place in just four days, bypassing typical delays caused by weather or onsite inefficiencies. From groundbreaking to substantial completion, Oldivai was finished in 310 days, shaving weeks off traditional construction timelines.

Challenges and Lessons Learned: Smarter Construction Every Step of the Way

Every challenge faced during the development of this project became an opportunity to refine modular construction processes. These obstacles not only shaped the Project Zero’s success but also established a framework for improving future developments.

Think Lifecycle, Build Smarter

The journey from factory fabrication to tenant move-in requires planning for every phase of a building’s lifecycle. At Oldivai, the team embraced a “start with the end in mind” philosophy. Features like standardized crawl space and attic access simplified future maintenance, ensuring the building functioned efficiently long after completion. This forward-thinking approach highlighted the importance of designing for long-term usability—not just immediate results.

Streamlining Communication

Early misalignments between architectural and modular plans caused delays and confusion, underscoring the need for clear documentation and communication.

  • Solution: A unified labeling system and centralized digital repository ensured that all stakeholders—from architects to contractors—worked from the same, up-to-date information.
  • Result: Improved consistency across teams, reduced miscommunication, and faster resolutions to onsite challenges.
JacksonMain-Picture3_1200x807

Fire Safety and Critical Systems Coordination

Ensuring compliance with fire safety requirements was a recurring challenge. Factory and onsite integration revealed the need for better coordination in critical systems like plumbing and fire suppression.

  • Solution: The team expanded zones for fire suppression systems and standardized plumbing bays to simplify installation. Detailed firestopping designs were also integrated into the architectural set to meet inspection standards.
  • Result: These adjustments avoided costly delays and have become a new standard for future modular projects.

Continuous Improvement

Modular construction thrives on iteration. Every success and setback at Oldivai informed a scalable framework for the future. Lessons weren’t just learned—they were applied, proving that modular isn’t just about speed but about smarter, more reliable results.

  • Standardization for Simplicity: Consistent fixtures, finishes, and system designs reduced variability and accelerated production.
  • Flexibility for the Unexpected: Challenges like fire safety revisions reinforced the importance of adaptability, ensuring that future projects are equipped to handle surprises.

Continuous Improvement

The insights from Oldivai on 31st offer practical guidelines for future modular developments:

  1. Design for the Lifecycle: Plan beyond completion—incorporate features that simplify maintenance, upgrades, and tenant satisfaction.
  2. Invest in Systems: Clear documentation, precise Oldivai on 31st Level 1 Floorplan labeling, and real-time updates prevent errors and build trust across teams.
  3. Standardize for Scalability: Uniformity in fixtures and finishes ensures consistent quality and reduces variability in production.
  4. Embrace Feedback: Every project provides lessons. Use them to refine processes and create smarter solutions.
JacksonMain-Picture5_800x1200

Cost Effectiveness

With a total cost of $2,692,850, Oldivai on 31st demonstrated that cost savings don’t come from cutting corners—they come from doing things right. Time is money, and Project Zero proved that faster construction saves both.

Conclusion: Building Better, Smarter, and Faster

For Jackson | Main Architecture and Oldivai Capital, Project Zero isn’t just a success—it’s a promise. This project demonstrates that better, faster, and smarter construction is achievable without compromising durability or design. For tenants, it offers a home they can trust, built to the highest standards. More than a single modular project, Oldivai on 31st is the foundation of a larger vision—one that extends far beyond Spokane and will shape housing solutions for years to come.

More from Modular Advantage

Housing Without Borders: Go Global with Haskell Modular Solutions

With the capacity to service over 15 diverse markets across multiple continents, Haskell is the reliable choice for our 80% repeat client base no matter how their needs evolve. So, when a longstanding client—typically known for their large-scale, institutional buildings—engaged Haskell with a very different need—multinational
housing projects—Haskell knew exactly what approach to take.

ProSet Co-founder Shares Expertise to Help Ensure Safe and Secure Modular Connections in Colorado

ProSet co-founder Matt Mitchell created and teaches an 8-hour course, based on Colorado’s modular installation regulations.

Women in Construction – Reflections on a Journey, Then and Now

From industry veteran Laurie Robert, a retrospective for women who are thinking about entering the modular construction industry or are looking to elevate their current position into leadership.

This Year’s Offsite Construction Summits Put Regional Priorities and Industry Realities in Focus

With Summits scheduled for Toronto, Los Angeles, Denver, Washington, DC, and Houston, this year’s series will connect manufacturers, designers, developers, contractors, public officials, and end-users around the practical use of offsite delivery in their own markets.

Affordable Housing, One Module at a Time

For builders and developers, modular factories offer significant scheduling and cost efficiencies compared with traditional site-built construction, regardless of whether the final product is workforce housing, single family homes, or apartment buildings.

Advancing Modular Housing Policy in California: An Interview With Tyler Pullen of Terner Labs/UC Berkeley’s Terner Center for Housing Innovation

Artificial intelligence is no longer a future concept in modular construction—it is already reshaping how complex buildings are evaluated, designed, and delivered.

Europe’s Modular Market Is Expanding, but Consistency Still Matters

Artificial intelligence is no longer a future concept in modular construction—it is already reshaping how complex buildings are evaluated, designed, and delivered.

How Stack Modular Is Using AI to De-Risk Mid- to High-Rise Modular Construction

Artificial intelligence is no longer a future concept in modular construction—it is already reshaping how complex buildings are evaluated, designed, and delivered.

Gearing Up for the 2026 World of Modular

The Modular Building Institute (MBI) is bringing its global World of Modular (WOM) conference and tradeshow back to Las Vegas in April, and with it comes some of the industry’s best opportunities for networking, business development, and education.

New High-Rise Modular Apartment in Abu Dhabi Points Toward the Future of Multifamily Construction

Eagle Hills International Properties chose the BROAD Holon Building for a 16-story market rate apartment building in Zayed City, a central business district of Abu Dhabi. The project highlights the potential of the Holon system of volumetric modular construction to accelerate housing delivery.