Parkhurst Elementary School Modular Classroom Additions

The Parkhurst Elementary School in Winchester, MA, has recently undergone an expansion of 13,074 square feet. Due to renovations at the neighboring Lynch School, students were temporarily relocated to Parkhurst. Modular construction was chosen as the preferred method to accommodate the influx of students and prepare for the start of the 2023-2024 school year.

Lynch Elementary School at Parkhurst serves 466 students from kindergarten to grade five. The newly added space includes 15 modules set in the old faculty parking lot. The modular classrooms were strategically placed to ensure compliance with state codes and to maximize available space. Each classroom is spacious and equipped with motion-sensing lights and conduits to install the necessary tech for the teachers. To ensure staff comfort, the design includes two faculty restrooms, multi-stall boys’ and girls’ bathrooms. The original RFP proposed an aluminum ramp to connect to the new parking lot, but Triumph Modular proposed a redesign that included an asphalt walkway with a gentler incline. This new walkway leads to a larger parking lot for staff and buses, with a designated drop-off area for the students. Subcontractors installed black powder-coated steel handrails on the aluminum decking, creating a seamless transition between the asphalt and the ramp while maintaining ADA compliance.

Despite challenges such as the unusually rainy summer season and the removal of a large amount of ledge from the site of the new parking lot, the project was completed on time and within budget. Triumph Modular’s expertise and ingenuity, as well as careful planning and logistical mapping, ensured that the project was a success. The town administrators were highly collaborative and worked with us when issues arose during the project.

The success of this project was made possible due to open communication with the municipalities and neighbors. Triumph Modular is proud to have been a part of the Winchester community and provided the children of Lynch Elementary School at Parkhurst with a safe and quality learning space for the next two years.

The Challenge

  • The classroom modules are placed in the existing school parking lot.
  • Constrained site space for the modular classrooms.
  • Unusually rainy season, delaying scheduled work and potentially impacting cost.
  • Thickly settled neighborhood.
  • Narrow and sloped delivery route for the modular classrooms.

The Solution

  • Creating a parking lot by paving over a baseball field.
  • Each unit had to be designed individually creating variable classroom sizes.
  • Negotiating with sub-contractors.
  • Our site supervisor constantly and consistently communicated with neighbors. Making them aware of upcoming work and any impact.
  • Several logistical plans routed to account for roads and trees.

The Results

  • A long-term permanent solution with additional parking spaces and a safer bus drop-off area for students to get into school.
  • The units were able to fit perfectly in the allotted space and maintain code compliance.
  • Our schedule stayed on track and our bid met budget.
  • Collaboration and communication with the town municipalities and administration.
  • Units were delivered without issue by smaller toters.

More from Modular Advantage

Mind the Gap: The Interface Between Onsite and Offsite Construction

Every design for manufacture and assembly (DfMA) project — modular, mass timber, or panelized — is really two projects joined at a seam. One is built in a controlled factory to millimeter tolerances; the other in the field, in weather, to the looser tolerances of poured concrete and human hands. Between them sits an interface: where the factory’s precision meets the site’s reality.

Rules, Rails & Repeatability: Applying DfMA to Modular Healthcare

DfMA offers several advantages for healthcare projects, with faster delivery among the most valuable. Schedule matters when building new facilities, expanding campuses, renovating existing space or bringing care closer to communities that need it.

Precision and Possibility: Demands of DfMA and What Modular Mass Timber Makes Possible

Mass timber does not automatically create an efficient modular building. Its precision makes early coordination more important: fabricated components will accurately reproduce both the team’s solutions and its mistakes. The material’s advantages are realized only when supported by an equally precise design and delivery process.

Catch It in the Factory, Not in the Field: Smarter Testing for Modular Builds

Integrating watertightness and airtightness testing into factory workflows transforms quality assurance from a reactive process into a proactive commissioning strategy. It ensures that every module shipped is field ready and resilient for transportation while also supporting the ability of the modular construction industry to make buildings better.

Modular Construction Contracts: Key Considerations for Successful Canadian Projects

Starting a modular project with a well-developed contract protects both the owner and the contractor. It will help keep the project on track and on budget, and it will improve quality from the factory floor to final installation on-site.

Modular by Design: Turning Architecture into a Manufacturing System

Modular construction is often presented as a faster way to build. Speed, however, is only one part of its value. The larger opportunity is to create a coordinated design and production system that improves quality, reduces uncertainty, and allows a building to move efficiently from concept design through manufacturing, transportation, installation, and completion.

Repeatability Begins with Trust: What Alora at Dry Creek Reveals About Scaling Modular Housing

Alora at Dry Creek, a 329-unit, multifamily community comprising five four-story buildings in Centennial, Colorado, demonstrates how repeatable design, standardized manufacturing and early collaboration can work together to create a model that is not only faster to deliver, but easier to replicate across future projects.

T.R. Arnold: The Art of Third-Party Inspections

T.R. Arnold (TRA), a third-party inspection company in Elkhart, Indiana, contracts with modular manufacturers across the US. Manufacturers register with each state to which they intend to send their modules and may be required to hire a third-party inspection company.

Creating an ‘Ecosystem for Innovation:’ 50+ Years of Modular Construction Oversight in Virginia

Virginia’s modular building program began in 1973, with the implementation of the Virginia Industrialized Building Unit and Mobile Home Safety Regulations. Now it’s leading the country in modular code adoption.

Understanding Thermal Barriers Compliance Methods & Emerging NFPA-275 Foam Plastic Technologies

New fire barrier technologies are improving total costs and margins in major areas of construction, such as commercial, government, union and prevailing wage projects. These benefits translate into other large fringe areas, such as agriculture, commercial cold storage facilities, grow houses, outbuildings, military and aviation hangars.