Art²Park – A Creative Application of Modular and Conventional Construction
George W. Runkle III, MS, PE, SE, is the president of Runkle Consulting, Inc.
In the heart of downtown Orlando, an innovative project called Art²Park is redefining how modular and conventional construction methods can be integrated to create dynamic, community-driven spaces.
What is Art²Park?
As described on the Downtown Orlando website, “Art² is an urban pocket park in downtown Orlando featuring food vendors, craft beverages, outdoor seating, and murals celebrating local art.”
The project serves as both a destination and a statement piece—combining art, food, and social gathering within a compact, efficiently designed space. What makes Art²Park unique is not just its program, but its construction: it fuses repurposed modular shipping containers with traditional structural steel and concrete systems, creating a visually striking and structurally robust urban park building.
How It Was Constructed
The design and construction of Art²Park reflect a sophisticated blending of modular and conventional techniques, demonstrating how the two can complement each other in both form and function.
Modular Core
At the heart of the project lies the modular core, built from repurposed shipping containers. These containers form the central portion of the two-story structure, housing concession spaces and other service areas. More than just functional enclosures, the containers serve as the structural backbone of the entire complex.
Conventional Framing and Decks
The building features expansive decks that create open, elevated gathering spaces:
- The upper deck is framed in structural steel with a composite concrete/steel deck system, providing both strength and stiffness.
- The lower level consists of a slab-on-grade foundation supporting open seating and circulation areas.
- A CMU stairwell provides enclosed access, while an open stairwell maintains visual openness.
- A steel-framed elevator shaft with light-gauge steel panel enclosures provides vertical circulation and accessibility.
Program and Layout
First Floor Enclosures:
- Concession/dining area
- Restrooms
- Art store
- Stairs and utility rooms
Second Floor Enclosures:
- Concession area
- Storage
- Restroom
- Stairs
- Audio-visual room
A distinctive feature is the large outdoor screen, suspended from a cantilevered steel frame, which anchors the park’s entertainment and event space.
Structural Synergy Between Modular and Conventional Systems
One of the most significant engineering achievements of Art²Park is how the modular portion of the structure contributes to the performance of the entire building. The shipping containers provide critical lateral resistance, acting as the primary wind-resisting system for the complex.
The second-floor deck functions as a rigid diaphragm, transferring lateral forces efficiently to the container walls. This approach allowed the design team to eliminate the need for conventional cross bracing or moment frames, substantially reducing steel tonnage and foundation demands. The result was a more open, cost-effective, and visually appealing design.
Even though the modular portion represents a relatively small share of the building’s overall footprint, it provides nearly all of the lateral stability—demonstrating the structural advantages of integrating container modules strategically within hybrid construction.
Why Containers?
For this project, the City chose modular/container construction due to the perceived temporary nature of the construction type. Because this project is located in the heart of Downtown on a site suited to a high-rise, it was meant to be temporary, with the understanding that temporary could last up to 20 + years. Containers were the logical vessel; they provided the durability and character the project deserved.
“For us,” said Max Brito, project architect at Rhodes + Brito Architects in Orlando, “the most significant benefit was the industrial aesthetic inherent to the material, along with the cost savings that come with a fully intact structural shell.”
Had traditional construction been chosen, “it would have been a challenge to match the containers' character. The building's size would probably have grown, and unfortunately, taken more space from the adjacent urban park. The park creates an outdoor living room that can morph into other uses, such as a concert space. So, the space is very valuable.”
Advice for Developers
“It's imperative that you hire a structural engineer with experience with container construction,” says Brito. “This will ensure that the designers take into account the nuances of container construction and understand its limitations. Efficiency comes from accommodating the nature of the container rather than trying to make it into something it is not. Also, the developer needs to be mindful of the spatial limitations and ensure the project's programming can adapt to those parameters.”
A New Model for Urban Design
Art²Park is more than a park building—it’s a demonstration of what modular construction can achieve when thoughtfully integrated with traditional materials. The use of shipping containers provided not only speed and sustainability benefits but also a powerful structural core that simplified and strengthened the rest of the building.
By combining engineering efficiency, architectural creativity, and community purpose, Art²Park stands as a model for the future of modular-conventional hybrid design in urban environments.
More from Modular Advantage
MBI Town Halls 2026: Reflections from Boston
By the end of 2026 MBI’s Government Affairs team will have traveled over 6,000 air miles to bring Town Hall events to five different cities in two countries.
Mind the Gap: The Interface Between Onsite and Offsite Construction
Every design for manufacture and assembly (DfMA) project — modular, mass timber, or panelized — is really two projects joined at a seam. One is built in a controlled factory to millimeter tolerances; the other in the field, in weather, to the looser tolerances of poured concrete and human hands. Between them sits an interface: where the factory’s precision meets the site’s reality.
Rules, Rails & Repeatability: Applying DfMA to Modular Healthcare
DfMA offers several advantages for healthcare projects, with faster delivery among the most valuable. Schedule matters when building new facilities, expanding campuses, renovating existing space or bringing care closer to communities that need it.
Precision and Possibility: Demands of DfMA and What Modular Mass Timber Makes Possible
Mass timber does not automatically create an efficient modular building. Its precision makes early coordination more important: fabricated components will accurately reproduce both the team’s solutions and its mistakes. The material’s advantages are realized only when supported by an equally precise design and delivery process.
Catch It in the Factory, Not in the Field: Smarter Testing for Modular Builds
Integrating watertightness and airtightness testing into factory workflows transforms quality assurance from a reactive process into a proactive commissioning strategy. It ensures that every module shipped is field ready and resilient for transportation while also supporting the ability of the modular construction industry to make buildings better.
Modular Construction Contracts: Key Considerations for Successful Canadian Projects
Starting a modular project with a well-developed contract protects both the owner and the contractor. It will help keep the project on track and on budget, and it will improve quality from the factory floor to final installation on-site.
Modular by Design: Turning Architecture into a Manufacturing System
Modular construction is often presented as a faster way to build. Speed, however, is only one part of its value. The larger opportunity is to create a coordinated design and production system that improves quality, reduces uncertainty, and allows a building to move efficiently from concept design through manufacturing, transportation, installation, and completion.
Repeatability Begins with Trust: What Alora at Dry Creek Reveals About Scaling Modular Housing
Alora at Dry Creek, a 329-unit, multifamily community comprising five four-story buildings in Centennial, Colorado, demonstrates how repeatable design, standardized manufacturing and early collaboration can work together to create a model that is not only faster to deliver, but easier to replicate across future projects.
T.R. Arnold: The Art of Third-Party Inspections
T.R. Arnold (TRA), a third-party inspection company in Elkhart, Indiana, contracts with modular manufacturers across the US. Manufacturers register with each state to which they intend to send their modules and may be required to hire a third-party inspection company.